Acceptance tests using different clients concurrently. Environment deployed from packages.

Build: #3280 was successful

Job: QoS was successful

user deletes qos requirements to file using client2 and using client1 sees that there is no qos requirements to file[1oz 1op 1oc-web GUi-RESt]: Test case result

The below summarizes the result of the test " user deletes qos requirements to file using client2 and using client1 sees that there is no qos requirements to file[1oz 1op 1oc-web GUi-RESt]" in build 3,280 of Onedata Products - mixed acceptance pkg - QoS.
Description
user deletes qos requirements to file using client2 and using client1 sees that there is no qos requirements to file[1oz 1op 1oc-web GUi-RESt]
Test class
mixed.scenarios.test_qos
Method
test_user_deletes_qos_requirements_to_file_using_client2_and_using_client1_sees_that_there_is_no_qos_requirements_to_file[1oz_1op_1oc-web GUI-REST]
Duration
43 secs
Status
Successful